110113 Site Visit


AS overview


Assembly plinth overview


Metsec to plenum underway


Additional works to make good lintol/ reveal OT.ED.00.02


Link steelwork- HRW to finalise reveal detail- CVA instruct


Rigid insulation to parapet CL GL/ C


DGT GRP to CL gambrel underway


Ditto


HCL to confirm closing of head flashing to CL.RL.03.01


AS overview


CL overview- batten for roofing commenced to North Elevation


Revised verge abutment to parapet


Battening/ rooflight


DGT applied mesh awaiting verge batten


Sentry/ urinal divider installed


Link blockwork complete


TEK vents 2FL on site


Installation of TEK commenced- deep reveal flashing


Head detail where conflict with ringbeam downstand


Access rooflight- CL stair 2


Brick slips to chimney


Intumescent paint completed to CL link GFL


Overview- Ingrave Road


Gas entry- AS


Detail- awaiting hard landscaping


Repairs to Ingrave Road wall- rates submitted- o/all price requ'd- HCL/ Global


Mortar to be raked out over lintol


Class link brickwork underway


Stair 2 plaster 1-2FL underway


Cubicles/ vanity unity CL 1fl


CVA to confirm window reveal details


GFL Cl corridor- mist coat applied


CVA to confirm scope for Queens slurry treatment