110127-28 Site Visit
Tiling now commenced to Classroom block north elevation
Repairs to remaining areas Otway externally
Arch repair/ infill
Otway interior continues- awaiting plaster 1fl
Template from Lambs on site for arch
Club tiles/ lunettes complete to Otway GFL
Tiles to be instructed to fireplace
Colour to be confirmed for Otway cills
Chimney side linings now stepped back
Perimeter wall to be marked up for accurate repointing/ replacement quote- CVA
COI required for 2fl lining to chimney frame- back-to-back beads/ skim- HCL
DGT to provide closing piece to hipped roof element
Flush rooflight- tags for lightning protection required
Pattern tiling underway
Cut to gable end requires attention GL A/9
Pattern tiles
Assembly overview- roof battening commenced
Door linings to Otway- unprotected
Assembly minstrels drylining/ rad position
Drylining to bulkhead/ minstrel's gallery