110127-28 Site Visit


Tiling now commenced to Classroom block north elevation


Repairs to remaining areas Otway externally


Arch repair/ infill


Otway interior continues- awaiting plaster 1fl


Template from Lambs on site for arch


Club tiles/ lunettes complete to Otway GFL


Tiles to be instructed to fireplace


Colour to be confirmed for Otway cills


Chimney side linings now stepped back


Perimeter wall to be marked up for accurate repointing/ replacement quote- CVA


COI required for 2fl lining to chimney frame- back-to-back beads/ skim- HCL


DGT to provide closing piece to hipped roof element

Flush rooflight- tags for lightning protection required



Pattern tiling underway


Cut to gable end requires attention GL A/9


Pattern tiles


Assembly overview- roof battening commenced


Door linings to Otway- unprotected


Assembly minstrels drylining/ rad position


Drylining to bulkhead/ minstrel's gallery