Clearance for balustrade limited to Assembly Hall lobby 1FL
Blockwork to fineline screens AS complete GL 14
HCL/ CVA to liaise regarding support structure for acoustic reflecting panels
MF7 support centres require min. 1200mm centres- steelwork above provides adequate fixings for drops. Classroom 2fl- GL A-B- classrooms- flat areas of ceilings
MF7 support centres require min. 1200mm centres- steelwork above provides adequate fixings for drops. Classroom 2fl- GL B-C corridors- flat areas of ceilings
Bulkhead to be formed to Psychology Classroom for electrical cable containment
CVA to confirm setting out of Classrooms 11 & 16
CVA to confirm triangulated panel- classroom 12 2fl
Awaiting 'I' studs- now instructed to raked areas 2 fl classrooms
Acoustic stopping required high level to blockwork- classroom block
Fireborn cappings underway to assembly hall parapet
Overflow detail to be as classroom block