Monday, 21 February 2011
110217+18 Site Visit
Roof overview
Ditto- tiling ongoing
Cl valley underway
CL valley- interface between lift overrun/ access and tile- CVA to advise
gambrel roof- tiling battens underway
storm flashing- mastic to junction required full height GL 1
DGT cover flashing now fitted GL 1/C
GL 1/D awaiting overflow pipe
Tiling commenced GFL CL block
CVA to forward detail of acoustic panel interface with wall high level CL stairs
CL stair 1 steel completed
Flush tap installed GL 1/C
Ingrave Road overview
Classroom roof complete north elev, awaiting chimney lids/ capping
Completion of plaster GFL toilets
Edge bead interface to all internal facing brickwork chimneys
Fire curtain setting out to be revised- CVA
AS minstrels gallery ceiling alignment
Lambs arch bricks on site
Ditto
Otway arch now underway
Ditto
Fixed tiered seating detail AS 1FL
Ditto- overview
Brickwork GL K AS hall
Prep for capping GL K GFL
CL link head detail/ interface w/ joinery tbc
CVA to confirm joinery benching fixing detail 1FL Otway
Bulkhead Otway GL 14
Acoustic ceilings underway GFL Otwya
Ditto
Targetti lighting installation commenced Otway GFL
Light switch Otway teapoint to be repositioned- CVA to instruct