Monday, 21 February 2011

110217+18 Site Visit


Roof overview


Ditto- tiling ongoing


Cl valley underway


CL valley- interface between lift overrun/ access and tile- CVA to advise


gambrel roof- tiling battens underway


storm flashing- mastic to junction required full height GL 1


DGT cover flashing now fitted GL 1/C


GL 1/D awaiting overflow pipe


Tiling commenced GFL CL block


CVA to forward detail of acoustic panel interface with wall high level CL stairs


CL stair 1 steel completed


Flush tap installed GL 1/C


Ingrave Road overview


Classroom roof complete north elev, awaiting chimney lids/ capping


Completion of plaster GFL toilets


Edge bead interface to all internal facing brickwork chimneys


Fire curtain setting out to be revised- CVA


AS minstrels gallery ceiling alignment


Lambs arch bricks on site


Ditto



Otway arch now underway


Ditto


Fixed tiered seating detail AS 1FL


Ditto- overview


Brickwork GL K AS hall


Prep for capping GL K GFL


CL link head detail/ interface w/ joinery tbc


CVA to confirm joinery benching fixing detail 1FL Otway


Bulkhead Otway GL 14


Acoustic ceilings underway GFL Otwya


Ditto


Targetti lighting installation commenced Otway GFL


Light switch Otway teapoint to be repositioned- CVA to instruct