Friday, 25 February 2011

110224 Site Visit


Overview from Ingrave Road


Classroom 12- ceiling triangulation set out- CVA to forward


Otway arch complete pointed


AS- GFL penetrations made for plenum grilles


Fineline AS windows/ doors on site awaiting installation


Link 1FL- from AS to OT


Acoustic flooring installation underway 1FL Otway


Mist coat wall colours GFL underway Otway


Acoustic ceilings/ light fittings Otway


CVA to instruct feature bead adjacent feature brickwork


Classroom 2FL linings complete Classroom 15


CL 2FL corridor airtightness detail


AS scaffold strike underway


CVA to instruct phenyl resin board to upstand/ overclad


DGT detail GL 1 still required between gutter runs


Sixth Form Centre Overview from Chimney scaffold


CL valley tiling/ chimney scaffold strike underway