110224 Site Visit
Overview from Ingrave Road
Classroom 12- ceiling triangulation set out- CVA to forward
Otway arch complete pointed
AS- GFL penetrations made for plenum grilles
Fineline AS windows/ doors on site awaiting installation
Link 1FL- from AS to OT
Acoustic flooring installation underway 1FL Otway
Mist coat wall colours GFL underway Otway
Acoustic ceilings/ light fittings Otway
CVA to instruct feature bead adjacent feature brickwork
Classroom 2FL linings complete Classroom 15
CL 2FL corridor airtightness detail
AS scaffold strike underway
CVA to instruct phenyl resin board to upstand/ overclad
DGT detail GL 1 still required between gutter runs
Sixth Form Centre Overview from Chimney scaffold
CL valley tiling/ chimney scaffold strike underway