Friday, 11 February 2011

110210 Site Visit


Otway 2fl window cill painted


modified CVA detail to fineline head requ'd


CVA to forward levels/ falls of AS link roof



AS cappings complete


Otway window repaairs GFL underway


CVA to forward spec to accompany mark up of Ingrave Road wall repairs on site w/ Global


CL link rooflight on site awaiting install


Plaster of arches underway to Otway


CVA to adjust ceiling set out to avoid drop ceiling obscuring apex to arch


All metalwork to Otway high level to be painted


Plinth to CL link underway- bricklight recesses set out


Conflict between blockwork and pipework to AS green room nib GL K/15- parking zone for folding sliding door- requires HRW comment


CL entry court


CVA to adjust set out of ceiling face to Class 16- to maintain
interface with block/ plaster


Beads omitted to classroom 14 adjacent brick


Framing to 2fl wall linings adjacent TEK vents commenced


I studs progressing to framing 2fl ceilings


North elevation pattern tiling complete


Zone for bulkhead to stair 2 2fl


Stair 1 interface wall/ ceiling high level- CVA to confirm no radius/ fillet to acoustic panel edge.
Stair 2 similar.


TEK cill to CL.EW.01.19 projects too far- TEK to remake and refit


Fire curtain set out to be adjusted- conflict with steelwork- CVA/ HRW


CVA to confirm lining/ curtain track to side stage access head of opening


Stage height tbc.- Action CVA


Paint to fillets complete


Cappings to roof parapet


Special cappings to corners installed- awaiting overflows and final flashings


COI to be issued for adjusted dry fix ridge tile- HCL


Mock up of revised ridge tile

No comments: