Friday, 11 February 2011
110210 Site Visit
Otway 2fl window cill painted
modified CVA detail to fineline head requ'd
CVA to forward levels/ falls of AS link roof
AS cappings complete
Otway window repaairs GFL underway
CVA to forward spec to accompany mark up of Ingrave Road wall repairs on site w/ Global
CL link rooflight on site awaiting install
Plaster of arches underway to Otway
CVA to adjust ceiling set out to avoid drop ceiling obscuring apex to arch
All metalwork to Otway high level to be painted
Plinth to CL link underway- bricklight recesses set out
Conflict between blockwork and pipework to AS green room nib GL K/15- parking zone for folding sliding door- requires HRW comment
CL entry court
CVA to adjust set out of ceiling face to Class 16- to maintain
interface with block/ plaster
Beads omitted to classroom 14 adjacent brick
Framing to 2fl wall linings adjacent TEK vents commenced
I studs progressing to framing 2fl ceilings
North elevation pattern tiling complete
Zone for bulkhead to stair 2 2fl
Stair 1 interface wall/ ceiling high level- CVA to confirm no radius/ fillet to acoustic panel edge.
Stair 2 similar.
TEK cill to CL.EW.01.19 projects too far- TEK to remake and refit
Fire curtain set out to be adjusted- conflict with steelwork- CVA/ HRW
CVA to confirm lining/ curtain track to side stage access head of opening
Stage height tbc.- Action CVA
Paint to fillets complete
Cappings to roof parapet
Special cappings to corners installed- awaiting overflows and final flashings
COI to be issued for adjusted dry fix ridge tile- HCL
Mock up of revised ridge tile