Friday, 26 March 2010

100325 Site Visit


Assembly- MSW floor deck to Minstrels Gallery


Assembly- Penetrations for air plenum


Assembly- Adjusted steelwork connection


Assembly- Decking in progress


Assembly- Final steel to assembly hall plinth


Incomplete brickwork- Classroom block GL C/7


Cavity try to be cleared Classroom block GL C


Classroom block CL.EW.01.18 opening- slab recess not built, insulation wrong position


Classroom block CL.EW.01.18 opening- slab recess not built


Classroom block CL.EW.01.18 opening- brickwork to be single skin only to reveal


Classroom block CL.EW.01.18 opening- brickwork to be single skin only to reveal


Pattern brickwork complete GL 9


Footing commenced to link


Otway- steel support installed ground floor


Otway- steel support for chimney first floor


Visual link between Otway and Classroom block- slab to follow


Otway- service penetration high level GL I/12


MSW deck Assembly hall


Carpentry- plinth roof assembly hall


Pooling to assembly hall slab showing evidence of level change


Assembly Hall- adjusted steel connection GL 14/L-M


Scaffold progressing Assembly Hall

Thursday, 18 March 2010

100318 Site Visit


Assembly Hall block/ landing


Hydra lime pointing sample- for voussoirs- not brickwork


Terracotta installation commenced


Excavation for gas commenced


Inconsistencies to assembly slab


Assembly hall stair installed


Corner feature brickwork now completed GFL classroom block


Movement joint G/L 6/C- clarify position (1/2 brick from return)


Pattern to larger chimney- facing Queens G/L 1- clarify setting out


Lambs bricks on site


Survey of brickwork repair reveals extensive crack to Voussoir Otway G/L F/G 1st floor(noted to Otway mark ups on site)


Chimney brickwork blown


brickwork below cill blown (noted to Otway mark ups on site)


Lambs brick rubbed red specials


Lambs brick rubbed red specials- corner detail

Thursday, 11 March 2010

100311 Site Visit


Stair interface- classroom block


Stair 2 Classroom block


Otway first floor demolition-- Chimney 1 steels inserted


Scaffold reconfigured to allow link to commence


Cavity tray DPC GL 1


Opening formed for large chimney- openings to classrooms absent in blockwork


Omnia clean after pour


Omnia 1flr poured- 1 week curing required


missed movement joint GL 1 C/D


Contrasting brickwork GL 9


Motif with contrasting mortar- Classroom block


Motif/ mortar detail


Ground floor brickwork classroom complete