Friday, 26 March 2010
100325 Site Visit
Assembly- MSW floor deck to Minstrels Gallery
Assembly- Penetrations for air plenum
Assembly- Adjusted steelwork connection
Assembly- Decking in progress
Assembly- Final steel to assembly hall plinth
Incomplete brickwork- Classroom block GL C/7
Cavity try to be cleared Classroom block GL C
Classroom block CL.EW.01.18 opening- slab recess not built, insulation wrong position
Classroom block CL.EW.01.18 opening- slab recess not built
Classroom block CL.EW.01.18 opening- brickwork to be single skin only to reveal
Classroom block CL.EW.01.18 opening- brickwork to be single skin only to reveal
Pattern brickwork complete GL 9
Footing commenced to link
Otway- steel support installed ground floor
Otway- steel support for chimney first floor
Visual link between Otway and Classroom block- slab to follow
Otway- service penetration high level GL I/12
MSW deck Assembly hall
Carpentry- plinth roof assembly hall
Pooling to assembly hall slab showing evidence of level change
Assembly Hall- adjusted steel connection GL 14/L-M
Scaffold progressing Assembly Hall
Thursday, 18 March 2010
100318 Site Visit
Assembly Hall block/ landing
Hydra lime pointing sample- for voussoirs- not brickwork
Terracotta installation commenced
Excavation for gas commenced
Inconsistencies to assembly slab
Assembly hall stair installed
Corner feature brickwork now completed GFL classroom block
Movement joint G/L 6/C- clarify position (1/2 brick from return)
Pattern to larger chimney- facing Queens G/L 1- clarify setting out
Lambs bricks on site
Survey of brickwork repair reveals extensive crack to Voussoir Otway G/L F/G 1st floor(noted to Otway mark ups on site)
Chimney brickwork blown
brickwork below cill blown (noted to Otway mark ups on site)
Lambs brick rubbed red specials
Lambs brick rubbed red specials- corner detail
Thursday, 11 March 2010
100311 Site Visit
Stair interface- classroom block
Stair 2 Classroom block
Otway first floor demolition-- Chimney 1 steels inserted
Scaffold reconfigured to allow link to commence
Cavity tray DPC GL 1
Opening formed for large chimney- openings to classrooms absent in blockwork
Omnia clean after pour
Omnia 1flr poured- 1 week curing required
missed movement joint GL 1 C/D
Contrasting brickwork GL 9
Motif with contrasting mortar- Classroom block
Motif/ mortar detail
Ground floor brickwork classroom complete