Thursday, 11 March 2010

100311 Site Visit


Stair interface- classroom block


Stair 2 Classroom block


Otway first floor demolition-- Chimney 1 steels inserted


Scaffold reconfigured to allow link to commence


Cavity tray DPC GL 1


Opening formed for large chimney- openings to classrooms absent in blockwork


Omnia clean after pour


Omnia 1flr poured- 1 week curing required


missed movement joint GL 1 C/D


Contrasting brickwork GL 9


Motif with contrasting mortar- Classroom block


Motif/ mortar detail


Ground floor brickwork classroom complete