Thursday, 18 March 2010

100318 Site Visit


Assembly Hall block/ landing


Hydra lime pointing sample- for voussoirs- not brickwork


Terracotta installation commenced


Excavation for gas commenced


Inconsistencies to assembly slab


Assembly hall stair installed


Corner feature brickwork now completed GFL classroom block


Movement joint G/L 6/C- clarify position (1/2 brick from return)


Pattern to larger chimney- facing Queens G/L 1- clarify setting out


Lambs bricks on site


Survey of brickwork repair reveals extensive crack to Voussoir Otway G/L F/G 1st floor(noted to Otway mark ups on site)


Chimney brickwork blown


brickwork below cill blown (noted to Otway mark ups on site)


Lambs brick rubbed red specials


Lambs brick rubbed red specials- corner detail