100325 Site Visit


Assembly- MSW floor deck to Minstrels Gallery


Assembly- Penetrations for air plenum


Assembly- Adjusted steelwork connection


Assembly- Decking in progress


Assembly- Final steel to assembly hall plinth


Incomplete brickwork- Classroom block GL C/7


Cavity try to be cleared Classroom block GL C


Classroom block CL.EW.01.18 opening- slab recess not built, insulation wrong position


Classroom block CL.EW.01.18 opening- slab recess not built


Classroom block CL.EW.01.18 opening- brickwork to be single skin only to reveal


Classroom block CL.EW.01.18 opening- brickwork to be single skin only to reveal


Pattern brickwork complete GL 9


Footing commenced to link


Otway- steel support installed ground floor


Otway- steel support for chimney first floor


Visual link between Otway and Classroom block- slab to follow


Otway- service penetration high level GL I/12


MSW deck Assembly hall


Carpentry- plinth roof assembly hall


Pooling to assembly hall slab showing evidence of level change


Assembly Hall- adjusted steel connection GL 14/L-M


Scaffold progressing Assembly Hall