Friday, 30 July 2010

100730 Building Design Article

Sixth Form Centre featured in Building Design Magazine's Envelope Supplement:





100729 Site Visit


Otway brickwork GL E infill


Otway existing footing- discrepancy with original survey


Brick wall to misalign with underside of steel high level- CVA./ HRW to confirm to HUT how to proceed


valley board conflict to rooflights- Otway. CVA to advise


Ringbeam cast Otway


Insulation to be addressed where ill-fitting/ too short.


GL D- Classroom- brickwork not protected when concrete slab cut back


Brickwork to reveal damaged following cutting GL D


Hutton to propose remedial measures for stained/ damaged brickwork


Hutton to propose remedial measures for stained brickwork


Client approves painted soffitt- CVA to confirm colour


Ring beam- geometry to be addressed


'Doughnut' to chimney base


Classroom block roof steel commences


Classroom corridor GL B-C with steel frame in place


Roof steel spigot misaligned


No threshold differentiation to matwell GL 6-7


Chasing- NEE/ HUT to confirm extent/ areas for approval


Bases for acoustic vents- screed to UFH Classroom block GFL


Assembly hall GL P/14- rotate access to face reveal (also N/14)


Service diversion works underway


Relief work GL Q


Terminate cable tray short of opening to piano store GL 18- due to limited headroom


GL 14- Piano Store/ Side Stage- Should read FFL + 400mm


Plinth brickwork GL 20, 94 degree corner with wrapped motif


94 degree special


Plinth brickwork GL 20- awaiting red mortar pointing to motif


Sheetseal to be redone GL 14 P/Q


Sheetseal GL 14 to be addressed- tape/ seal


Reveal to brickwork GL P- pointing to be as facework elsewhere- this is not a movement joint


awaiting red mortar pointing to motif


Hit and miss brickwork to plantroom in progress


Gutter still awaiting remedial works by DGT


Ball guards required to High level assembly roof outlets


Insulation// seal required around windposts high level

Thursday, 22 July 2010

100721-22 Site Visit


Assembly GL 14 brickwork in progress


GL M/14- steel connection to link brickwork support requires attention- HRW/ HUT


Ditto


Classroom ringbeam nears completion


Classroom ground floor corridor soffitt elec trays installed incorrectly- drawing not issued/ approved- condemned


CVA to provide detail for differential movement to deep reveals 2nd flr Classroom


Conflict between lintel and windpost in several locations 2nd floor- HRW to confirm trim back acceptable


Ditto


Windpost installation classroom roof level


Cutout to plate required for downpipe GL M/18 assembly hall- HRW to confirm if acceptable


Chasing out Gfl classroom- HUT confirm positions/ extent to HRW


underfloor heating installation classroom 3


Screed to Praes over UFH


Cutout to plate required for downpipe GL M/14 assembly hall- HRW to confirm if acceptable


MJ to gridline P/14- cut bricks


GL P/14 return brickwork requires better pointing- as it is visible


Brickwork support GL 14


ply above opening GL 14


Brickwork relief GL Q detail


Brickwork relief GL Q


Brickwork relief GL Q


RWP high level GL L/18


Metsec high level installation underway


Infill insulation to Otway roof


insulation infill


Arch repair/ making good- HUT/ CVA to schedule all areas req'd


Infill brickwork to form opening for OT.EW.00.06


Plinth brickwork commenced GL K/19


Plinth brick GL 19


Motif before raked joints


To be as reference panel


'bullet holes' to headers


Snapped headers- cuts do not allow to be rotated in flemish bond plinth wall


low level brickwork GL K/17 to be rebuilt- misaligned