Sixth Form Centre featured in Building Design Magazine's Envelope Supplement:
Friday, 30 July 2010
100729 Site Visit
Otway brickwork GL E infill
Otway existing footing- discrepancy with original survey
Brick wall to misalign with underside of steel high level- CVA./ HRW to confirm to HUT how to proceed
valley board conflict to rooflights- Otway. CVA to advise
Ringbeam cast Otway
Insulation to be addressed where ill-fitting/ too short.
GL D- Classroom- brickwork not protected when concrete slab cut back
Brickwork to reveal damaged following cutting GL D
Hutton to propose remedial measures for stained/ damaged brickwork
Hutton to propose remedial measures for stained brickwork
Client approves painted soffitt- CVA to confirm colour
Ring beam- geometry to be addressed
'Doughnut' to chimney base
Classroom block roof steel commences
Classroom corridor GL B-C with steel frame in place
Roof steel spigot misaligned
No threshold differentiation to matwell GL 6-7
Chasing- NEE/ HUT to confirm extent/ areas for approval
Bases for acoustic vents- screed to UFH Classroom block GFL
Assembly hall GL P/14- rotate access to face reveal (also N/14)
Service diversion works underway
Relief work GL Q
Terminate cable tray short of opening to piano store GL 18- due to limited headroom
GL 14- Piano Store/ Side Stage- Should read FFL + 400mm
Plinth brickwork GL 20, 94 degree corner with wrapped motif
94 degree special
Plinth brickwork GL 20- awaiting red mortar pointing to motif
Sheetseal to be redone GL 14 P/Q
Sheetseal GL 14 to be addressed- tape/ seal
Reveal to brickwork GL P- pointing to be as facework elsewhere- this is not a movement joint
awaiting red mortar pointing to motif
Hit and miss brickwork to plantroom in progress
Gutter still awaiting remedial works by DGT
Ball guards required to High level assembly roof outlets
Insulation// seal required around windposts high level
Thursday, 22 July 2010
100721-22 Site Visit
Assembly GL 14 brickwork in progress
GL M/14- steel connection to link brickwork support requires attention- HRW/ HUT
Ditto
Classroom ringbeam nears completion
Classroom ground floor corridor soffitt elec trays installed incorrectly- drawing not issued/ approved- condemned
CVA to provide detail for differential movement to deep reveals 2nd flr Classroom
Conflict between lintel and windpost in several locations 2nd floor- HRW to confirm trim back acceptable
Ditto
Windpost installation classroom roof level
Cutout to plate required for downpipe GL M/18 assembly hall- HRW to confirm if acceptable
Chasing out Gfl classroom- HUT confirm positions/ extent to HRW
underfloor heating installation classroom 3
Screed to Praes over UFH
Cutout to plate required for downpipe GL M/14 assembly hall- HRW to confirm if acceptable
MJ to gridline P/14- cut bricks
GL P/14 return brickwork requires better pointing- as it is visible
Brickwork support GL 14
ply above opening GL 14
Brickwork relief GL Q detail
Brickwork relief GL Q
Brickwork relief GL Q
RWP high level GL L/18
Metsec high level installation underway
Infill insulation to Otway roof
insulation infill
Arch repair/ making good- HUT/ CVA to schedule all areas req'd
Infill brickwork to form opening for OT.EW.00.06
Plinth brickwork commenced GL K/19
Plinth brick GL 19
Motif before raked joints
To be as reference panel
'bullet holes' to headers
Snapped headers- cuts do not allow to be rotated in flemish bond plinth wall
low level brickwork GL K/17 to be rebuilt- misaligned
Subscribe to:
Posts (Atom)