Friday, 16 July 2010
100715 Site Visit
Classroom overview Ingrave Road
Assembly overview Ingrave Road
G/L Q- remove stretcher- poor face
Movement joint to relief brickwork
snots to be removed- brickwork cleaned generally G/L Q
Special corner G/L Q/14 w/ bed joint reinforcement
Brickwork support G/L 14 installed
Windposts for high level assembly
Detail low level diaper to be modified as ref panel- see below
stretcher and 2 No. headers to avoid exposed mortar joint to bottom of relief V
corner- cold bridge lightweight block detail G/L Q/ 18
Sheetseal detail test- CVA to confirm with Ancon
First fix mechanical
Windposts to Green room brickwork? HRW to confirm
Additional scope for Metsec beyond HRW drawings- HUT to issue sketch. HRW comment
Diaper/ relief mis-aligned- condemned 3 No. courses
Ditto
Rebuilt section- 4.30pm- acceptable
Higher level relief diaper to G/L Q/14
First fix elec- Classroom block
Ditto
First fix- schematic/ mock up
Concrete chimney base- now condemned following earlier warning regarding formwork- see link
posted 24.06.10- HUT to advise
Ringbeam in progress- classroom
Ditto
Ditto
Otway remaining floor installed
Instructed excavation/ make good complete to teapoint area
Additional non- solid floor revealed- COI to follow
G/L E- lintol works otway
OT.EW.01.03 reveal underway
Gabel detail complete
Junckers floor/ build up to be updated following discussion with approved installer on site- tolerance issue with substrate/ existing timbers.- CVA to update/ instruct