Thursday, 22 July 2010

100721-22 Site Visit


Assembly GL 14 brickwork in progress


GL M/14- steel connection to link brickwork support requires attention- HRW/ HUT


Ditto


Classroom ringbeam nears completion


Classroom ground floor corridor soffitt elec trays installed incorrectly- drawing not issued/ approved- condemned


CVA to provide detail for differential movement to deep reveals 2nd flr Classroom


Conflict between lintel and windpost in several locations 2nd floor- HRW to confirm trim back acceptable


Ditto


Windpost installation classroom roof level


Cutout to plate required for downpipe GL M/18 assembly hall- HRW to confirm if acceptable


Chasing out Gfl classroom- HUT confirm positions/ extent to HRW


underfloor heating installation classroom 3


Screed to Praes over UFH


Cutout to plate required for downpipe GL M/14 assembly hall- HRW to confirm if acceptable


MJ to gridline P/14- cut bricks


GL P/14 return brickwork requires better pointing- as it is visible


Brickwork support GL 14


ply above opening GL 14


Brickwork relief GL Q detail


Brickwork relief GL Q


Brickwork relief GL Q


RWP high level GL L/18


Metsec high level installation underway


Infill insulation to Otway roof


insulation infill


Arch repair/ making good- HUT/ CVA to schedule all areas req'd


Infill brickwork to form opening for OT.EW.00.06


Plinth brickwork commenced GL K/19


Plinth brick GL 19


Motif before raked joints


To be as reference panel


'bullet holes' to headers


Snapped headers- cuts do not allow to be rotated in flemish bond plinth wall


low level brickwork GL K/17 to be rebuilt- misaligned