Thursday, 22 July 2010
100721-22 Site Visit
Assembly GL 14 brickwork in progress
GL M/14- steel connection to link brickwork support requires attention- HRW/ HUT
Ditto
Classroom ringbeam nears completion
Classroom ground floor corridor soffitt elec trays installed incorrectly- drawing not issued/ approved- condemned
CVA to provide detail for differential movement to deep reveals 2nd flr Classroom
Conflict between lintel and windpost in several locations 2nd floor- HRW to confirm trim back acceptable
Ditto
Windpost installation classroom roof level
Cutout to plate required for downpipe GL M/18 assembly hall- HRW to confirm if acceptable
Chasing out Gfl classroom- HUT confirm positions/ extent to HRW
underfloor heating installation classroom 3
Screed to Praes over UFH
Cutout to plate required for downpipe GL M/14 assembly hall- HRW to confirm if acceptable
MJ to gridline P/14- cut bricks
GL P/14 return brickwork requires better pointing- as it is visible
Brickwork support GL 14
ply above opening GL 14
Brickwork relief GL Q detail
Brickwork relief GL Q
Brickwork relief GL Q
RWP high level GL L/18
Metsec high level installation underway
Infill insulation to Otway roof
insulation infill
Arch repair/ making good- HUT/ CVA to schedule all areas req'd
Infill brickwork to form opening for OT.EW.00.06
Plinth brickwork commenced GL K/19
Plinth brick GL 19
Motif before raked joints
To be as reference panel
'bullet holes' to headers
Snapped headers- cuts do not allow to be rotated in flemish bond plinth wall
low level brickwork GL K/17 to be rebuilt- misaligned