Friday, 30 July 2010
100729 Site Visit
Otway brickwork GL E infill
Otway existing footing- discrepancy with original survey
Brick wall to misalign with underside of steel high level- CVA./ HRW to confirm to HUT how to proceed
valley board conflict to rooflights- Otway. CVA to advise
Ringbeam cast Otway
Insulation to be addressed where ill-fitting/ too short.
GL D- Classroom- brickwork not protected when concrete slab cut back
Brickwork to reveal damaged following cutting GL D
Hutton to propose remedial measures for stained/ damaged brickwork
Hutton to propose remedial measures for stained brickwork
Client approves painted soffitt- CVA to confirm colour
Ring beam- geometry to be addressed
'Doughnut' to chimney base
Classroom block roof steel commences
Classroom corridor GL B-C with steel frame in place
Roof steel spigot misaligned
No threshold differentiation to matwell GL 6-7
Chasing- NEE/ HUT to confirm extent/ areas for approval
Bases for acoustic vents- screed to UFH Classroom block GFL
Assembly hall GL P/14- rotate access to face reveal (also N/14)
Service diversion works underway
Relief work GL Q
Terminate cable tray short of opening to piano store GL 18- due to limited headroom
GL 14- Piano Store/ Side Stage- Should read FFL + 400mm
Plinth brickwork GL 20, 94 degree corner with wrapped motif
94 degree special
Plinth brickwork GL 20- awaiting red mortar pointing to motif
Sheetseal to be redone GL 14 P/Q
Sheetseal GL 14 to be addressed- tape/ seal
Reveal to brickwork GL P- pointing to be as facework elsewhere- this is not a movement joint
awaiting red mortar pointing to motif
Hit and miss brickwork to plantroom in progress
Gutter still awaiting remedial works by DGT
Ball guards required to High level assembly roof outlets
Insulation// seal required around windposts high level