Friday, 30 July 2010

100729 Site Visit


Otway brickwork GL E infill


Otway existing footing- discrepancy with original survey


Brick wall to misalign with underside of steel high level- CVA./ HRW to confirm to HUT how to proceed


valley board conflict to rooflights- Otway. CVA to advise


Ringbeam cast Otway


Insulation to be addressed where ill-fitting/ too short.


GL D- Classroom- brickwork not protected when concrete slab cut back


Brickwork to reveal damaged following cutting GL D


Hutton to propose remedial measures for stained/ damaged brickwork


Hutton to propose remedial measures for stained brickwork


Client approves painted soffitt- CVA to confirm colour


Ring beam- geometry to be addressed


'Doughnut' to chimney base


Classroom block roof steel commences


Classroom corridor GL B-C with steel frame in place


Roof steel spigot misaligned


No threshold differentiation to matwell GL 6-7


Chasing- NEE/ HUT to confirm extent/ areas for approval


Bases for acoustic vents- screed to UFH Classroom block GFL


Assembly hall GL P/14- rotate access to face reveal (also N/14)


Service diversion works underway


Relief work GL Q


Terminate cable tray short of opening to piano store GL 18- due to limited headroom


GL 14- Piano Store/ Side Stage- Should read FFL + 400mm


Plinth brickwork GL 20, 94 degree corner with wrapped motif


94 degree special


Plinth brickwork GL 20- awaiting red mortar pointing to motif


Sheetseal to be redone GL 14 P/Q


Sheetseal GL 14 to be addressed- tape/ seal


Reveal to brickwork GL P- pointing to be as facework elsewhere- this is not a movement joint


awaiting red mortar pointing to motif


Hit and miss brickwork to plantroom in progress


Gutter still awaiting remedial works by DGT


Ball guards required to High level assembly roof outlets


Insulation// seal required around windposts high level