Thursday, 23 December 2010

101223 Site Visit


Assembly Hall- plinth scaffold partially struck


Ditto


Hall from ingrave Road


Windows installed w/ glass- GFL Classroom Block


Ditto


Adjacent Queens- shallow window reveals


Fixing detail CL.EW.00.14- head detail to be discussed- lintel higher internally than external


CL link GFL


Thrislington Sentry panels on site


Window to Praes


Insulation required to brickwork 2FL GL D/1


Acoustic seal to head of block to be completed to 1FL toilets- ceilings already installed


CL.01.25- containment interface with edge bead


CL.EW.02.23 head/ ringbeam to be recast


Assembly plenum now constructed behind bleacher seating


Assembly linings


Minor water damage GL 14 GFL- to be replaced once gutters completed


Assembly linings- structure for hanging acoustic reflector


OT windows GFL- OT.ED.00.04- CVA to confirm scope for refurb


Deputy Head 1 Office


Otway step GL H 1FL- 1 No. course brickwork may need to be reduced- CVA to advise


Chimney- slurry applied/ scaffold removed- Otway 1FL


Otway 1FL ceiling


CVA to confirm whether timber can be removed


Timber structure painting underway. CVA to advise on maintaining void over stair GL G-H

Friday, 17 December 2010

101216 Site Visit


Ceiling light fitting- mock up- 300mm recess to Otway required for fitting


GL Q- clearance required for timber panels/ access for rodding- CVA/ MFLLP to advise


Gas enclosure installed


Stress UK repair completed to 1FL arch Otway


Internal shot of classroom chimney


GFL windows on site awaiting installation


Movement joint to capping- HCL to confirm lapping of DPC where loose capping


Otway gulley detail to Otway gable end


Flashing work requires attention to tidy up- roof to Otway House


Ridge tile fixings/ trim to be tidied up


Scaffold removed to reveal structure + void, Otway House


Ditto


Draught seals installed to windows


Additional rot/ repairs required to windows- HCL to schedule those areas over/ above schedule refurb


Cill colour- CVA to forward


DGT profiles being fitted to classroom rooflights


Classroom block- windows fitted GFL- link sealed


Assembly plantroom- scaffold struck. Grille/ ducts to be adjusted- see SVR


2fl corridor- M&E 1st fix underway


Otway render hacked off and removed where live


Link 1fl- blockwork underway


GFL link- screed completed- movement joints required to Otway/ Classroom

Monday, 13 December 2010

101210 Site Visit


Linings to assembly hall complete- minor water ingress GL N


Assembly stair lining/ cross section to be issued- CVA


Lambs replacement arch underway Otway house


Movement joint required to screed- Classroom link/ Otway threshold GFL


GL E/6 brick plinth to be cut back for curtain walling


First delivery of Secco Windows on site


Ditto


Deeper 'z' section required for fixing of acoustic panel


CVA to forward interface details for Stair 2 balustrade


Movement joint needed between link and classroom block to screed 1FL


Fireproofing underway to CL plantroom 2FL- requires intumescent sealant


Drain in progress 2 FL plantroom


Air tightness detail to be reviewed to corridor 2FL classroom- CVA to update/ clarify


Interfaces/ gaps to be highlighted- 2FL classroom- Classroom 16


Water tank deck/ guarding installed 2FL classroom


Silicon seal to cill to be removed/ redone- Sealant as RAL 7022


DGT flashing profiles now on site for CL rooflights