Friday, 25 March 2011
110324 Site Visit
Green room glazing underway
Stair 1 lining underway
Top floor classroom decoration
Closing piece to curtain wall, classroom link GFL
Otway teapoint joinery complete
lining details forwarded to HCL for rooflight
Fixed joinery underway to 1fl careers library- CL link
Otway pastoral offices nearing completion 1FL
Latchway system underway to AS plinth roof
1FL Assembly link trench heating installed
CVA to confirm updated setting out around RWP.AS.08
AS stair glazing complete- awaiting linings
AS link
Classroom block- scaffold struck to link
AS GFL glazing to plinth nearing completion
Acoustic panel housing installed AS high level hall
AS link external- awaiting soffit panels
Fineline/ trench heating
AS link overview
Cracks over GL C CL.EW.00.14- monitor- HCL to repoint
Ditto
Tuesday, 22 March 2011
110321 Site Visit
Ingrave Road overview
Assembly Hall- windows installed
Otway- teapoint nearing completion
Otway scaffold struck
Ditto
Classroom link- 'no architrave' detail- agreed on site
2nd floor doors installation underway to classroom block
Revised classroom gambrel roof detail underway
Ditto
Tiling to link complete- issue with coping/ ridge tile- HCL to clarify/ CVA to advise
Fineline installation nearing completion
View over green roof/ Ingrave Road
View back to Otway through first floor link
View along screen- fritting omitted to last two panes in error- CVA to advise
first floor link glazing installed
Fineline windows installed ground floor assembly hall
2nd floor corridor classroom
Blue coping to trapezoid rooflight
Assembly acoustic panels on site awaiting installation
Friday, 18 March 2011
100317 Site Visit
Ingrave Road- overview with scaffold struck
Assembly Hall- windows installed 1st flr
AS- Fineline glazing installation underway to courtyard
CL link- curtain walling installation nearing completion
discrepancy to head/ cill- HCL to liaise with SecCo regarding interface with soffitt panels
Awaiting soffitt panel to reveal for completion- classroom north elevation
Classroom block-Library square overview
Assembly link- awaiting Fineline glass installation
Assembly interior- acoustic reflector panel installation nearing completion
CL stairs- tiling underway with contrasting nosing/ riser detail
Ditto
Classroom 12 lining complete- awaiting joinery
Classroom 16- window reveal complete
Classroom 16 - ceiling awaiting bead/ skim
Joinery scalloped pen rest detail to whiteboards
Overview
CL roof- adjustment required to trapezoid rooflight tiling perimeter
CL gambrel- detail not as drawn- to be reworked
Ditto- flashing girth to be greater/ no intermediate tile to transition
OT- Sealant to 1fl windows complete except OT.EW.01.08
Fineline rail overlooking plinth roof
Sleeve around hot pipes installed
Gulley installed to AS plinth
CVA/ HRW to forward guarding details- AS mezzanine- RHS
CVA/ HRW to forward guarding details- AS mezzanine- LHS
Central aisle cavity- for gate- CVA/ HRW to forward details
CVA to forward handrail details AS mezzanine
TEK vent to green room installed
External view- TEK green room vent
Glazing underway - AS green room
AS panelling frame nears completion
AS ceiling
AS Reflectors
AS court overview
HTP sample client supply locker delivered to staff room
WISA to match other joinery