Friday, 30 April 2010
100429 Site Visit
Brickwork overview classroom block
Classroom block brick over CL.ED.00.03 to be cleaned up- spattered with mortar
Mortar missing to facing bricks- GL8 north elevation
Detail for TSI Steels/ link/ classroom block to be forwarded/ instructed
Setting out of 1st floor Otway low wall 1st floor to be updated- survey of stairs out
Rebar to 2nd floor slab
Ditto
Metsec added to east elevation Assembly Hall- nets added
Services penetration required to plinth roof prior to framing up- to be removed
Handrail detail over window to be clarified
Otway basement now half-filled
Otway 1st floor low partition to stair
Rot to valley beam
Preparation for padstone pour 1st floor Otway
Assembly Hall upper reference panel underway
Reference panel face
Reference panel from corner with specials
Discrepancy to course 84- on corner
Discrepancy to bonding courses 76-78 to right elevation B (AS026 rev C2)
Discrepancy between courses 74 and 76 to main elevation A (AS026 rev C2)
brickwork not aligned- special corners unnecessarily cut
Special R4 cut unnecessarily course 78 right elevation(AS026 rev C2)
Classroom overview from Ingrave Road
Assembly Hall overview from Ingrave Road
Monday, 26 April 2010
100422 Site Visit
Reference panel for Assembly Hall rebuilt with stretchers over hit and miss now built frog-down
High level rubbed reds to Otway gable end
Chimney demolished- to be rebuilt
Good bricks to be retained for other repairs to Otway
Special corner bricks for reference panel from Ibstock- cut and glued with Epoxy- not thrown
Special corners for relief work sample- assembly high level
Ditto
Areas requiring packing in Otway- where new steelwork inserted for Chimney A
Roof truss does not align with retained pier GL G
GL E high level- Hutton to propose method, HRW to advise
Damp proofing to column stanchions
GL F high level- Hutton require instruction to underside of rafters
Otway gable ends clash- requiring short section of valley/ flashing detail and hopper. CVA to forward.
RIW LAC application reveals imperfections in slab- CVA to advise if Acceptable to RIW requirements
Corner detail GL Q 14- leading edge support of steel insulated panel to be confirmed/ support for gutter
Ditto
Ditto GL Q 16
Hutton still to confirm status of slab GL D- if not 20mm allowance will require cutting back
Omnia high level- grouting only to supporting edges- Hutton to follow with remainder/ gaps where not spanning
Ditto
CVA to confirm brick corbelling detail GL D7- alongside position of steel to link
Large chimney GL 1 under construction- still requires openings to be cut in block
Wednesday, 21 April 2010
100420 Site Visit
Assembly hall plinth reference panel- with wrapped corner pattern
86 degree corner
Hit and miss brickwork- some bricks mistakenly laid frog up- not frog down
Epoxy-filled frog- reds to be solids in actual plinth brickwork
Diamond pattern- requires pointing
Overview of hit and miss
High level detail- straps query for HRW
Blockwork to be reviewed in areas of cross-bracing to assembly hall