100408 Site Visit
Enterprise arrive to complete gas diversion- Ingrave Road
Gas diversions within site boundary- completes 09/04/10
Wall ties classroom block- not sufficient/ consistent embedment
Poor placement/ embedment of ties- G/L 1, 1st floor- to be rectified
Post fixed tie poorly fitted- G/L 9, 1st floor- to be rectified
Poor placing of ties in blockwork- G/L 1
Ditto
Ditto- all to be rectified
Link slab prep
Containment required for bricklights to G/L 7- FFL
Upstand formed G/L 7
Firrings added- plinth roof assembly hall
Minstrel's Gallery- concrete curing
Service penetrations required to steelwork- G/L K-L high level- as instructed HRW sketch
Assembly precast stair out of square
Precast stair- Hutton to rectify
Classroom beam prep- G/L D
Brickwork to be rebuilt around link steel, G/L C/6- classroom block
Ties to be removed, Classroom block G/L 9/B, GFL