Monday, 26 April 2010

100422 Site Visit


Reference panel for Assembly Hall rebuilt with stretchers over hit and miss now built frog-down


High level rubbed reds to Otway gable end


Chimney demolished- to be rebuilt


Good bricks to be retained for other repairs to Otway





Special corner bricks for reference panel from Ibstock- cut and glued with Epoxy- not thrown


Special corners for relief work sample- assembly high level


Ditto


Areas requiring packing in Otway- where new steelwork inserted for Chimney A


Roof truss does not align with retained pier GL G


GL E high level- Hutton to propose method, HRW to advise


Damp proofing to column stanchions


GL F high level- Hutton require instruction to underside of rafters


Otway gable ends clash- requiring short section of valley/ flashing detail and hopper. CVA to forward.


RIW LAC application reveals imperfections in slab- CVA to advise if Acceptable to RIW requirements


Corner detail GL Q 14- leading edge support of steel insulated panel to be confirmed/ support for gutter


Ditto


Ditto GL Q 16


Hutton still to confirm status of slab GL D- if not 20mm allowance will require cutting back


Omnia high level- grouting only to supporting edges- Hutton to follow with remainder/ gaps where not spanning


Ditto


CVA to confirm brick corbelling detail GL D7- alongside position of steel to link


Large chimney GL 1 under construction- still requires openings to be cut in block