Motif wrapping around 94 degree corner- GL N/20 Assembly


Hit and miss pattern with motif- GL K/17-19 Assembly


Ply infill for brickwork support- GL 14 Assembly


Insulation to peripheral storage areas- Assembly


Steels cut back for RWP GL Q/18 Assembly


Taped corners require attention GL Q/14 Assembly


Brickwork GL L over plinth element Assembly


Otway walls to offices GL 11/E-F Otway


Sleeper walls/ new wall plates Otway OT.00.03


Completion of decorative brickwork to gable end GL I/12 Otway


Repair of arch underway GL H/12 Otway


Electrical basket relocated Classroom GFL corridor-still no drawing issue for approval by NEE


Ditto


Steelwork spigot amended by TSI


TSI steelwork to classroom roof


Concrete spalling to several locations- HUT to forward proposals for remedial works to all locations

Ditto


Ringbeam GL C-D/4- requires remedial works/ repour as setting out is incorrect and beyond workable tolerances. Head of opening also cast incorrectly. HUT to forward proposals for remedial works for approval.


Trunking fitted with no accurate setting out information or mist coat to concrete work above


Screed works to Classroom GL C/1


Gas enclosure on site- awaiting confirmation of revised date for connection