Friday, 6 August 2010
100805 Site Visit
Motif wrapping around 94 degree corner- GL N/20 Assembly
Hit and miss pattern with motif- GL K/17-19 Assembly
Ply infill for brickwork support- GL 14 Assembly
Insulation to peripheral storage areas- Assembly
Steels cut back for RWP GL Q/18 Assembly
Taped corners require attention GL Q/14 Assembly
Brickwork GL L over plinth element Assembly
Otway walls to offices GL 11/E-F Otway
Sleeper walls/ new wall plates Otway OT.00.03
Completion of decorative brickwork to gable end GL I/12 Otway
Repair of arch underway GL H/12 Otway
Electrical basket relocated Classroom GFL corridor-still no drawing issue for approval by NEE
Ditto
Steelwork spigot amended by TSI
TSI steelwork to classroom roof
Concrete spalling to several locations- HUT to forward proposals for remedial works to all locations
Ditto
Ringbeam GL C-D/4- requires remedial works/ repour as setting out is incorrect and beyond workable tolerances. Head of opening also cast incorrectly. HUT to forward proposals for remedial works for approval.
Trunking fitted with no accurate setting out information or mist coat to concrete work above
Screed works to Classroom GL C/1
Gas enclosure on site- awaiting confirmation of revised date for connection