Monday, 23 August 2010
100818 Site Visit
Rain water still draining onto Assembly Hall floor. Concern over insulation getting wet.
Hutton have closed up rooflights to control water ingress, will close up windows asap.
Foil backed insulation to Assembly Hall along GL.Q has been torn and needs to be repaired.
Level reached on Assembly Hall brickwork.
Stack bond 245 reveal to Assembly Hall windows to be resolved.
Hutton confirm that lintol to GL.L/14-15 has been installed as instructed.
Slab level at threshold to Assembly plant to be amended.
New joists to Otway.
Former cellar windows to be boarded up internally. Architraves and beading removed to allow level finish with adjacent plaster.
Former cellar windows to be boarded up internally and reglazed externally with toughened, enamelled glass.
Replacement terracotta mullion and transom installed in Otway large stair window
Otway re-roofing eaves issues discussed with sub-contractor. Amendments agreed to fascia board depth and ventilation strategy.
Remade junction of Otway gables awaiting leadwork.
Insulation not installed to rafters in Otway.
Insulation to be cut around steelwork, Otway roof.
Hutton raise issue of steel in area of first floor link from Otway to Assembly, clashing with existing voussoirs arch. CVA to discuss with HRW.
Mist coat to Classroom omnia slabs under way. CVA to inspect at next site visit.
Classroom ground floor windows at GL.C. Fixing of window head to structure to be checked.
Recast raked ring beam complete. Hutton require connection of roof steel to be clarified.
Classroom block brickwork to date.
Fixing of windpost above window at GL.1/C. Will require raising and additional fixing to ring beam to avoid window head.
Checking brickwork levels on site, these work with respect to structure. One issue is that windpost heights need to be checked based on Hutton site dimensions.