Thursday, 12 August 2010

100811 Site Visit


Otway ceilings- CVA to schedule making good notes following site visit


Hearth to be maintained- timber floor to terminate to perimeter at same level


Roof awaiting insulation


Valley boards installed


Awaiting insulation- valley board installed


brickwork high level GL E 1st floor


Window to former basement- CVA detail update to follow


Sleeper walls- HUT COI to follow


Brick pattern amended to classroom


Insulation overcut to CL.ED.00.02


Concrete spalling to majority of ring beam high level- HUT to forward proposals for remedial works for comment


Ring beam GL C-D/4 to be removed/ recast


Spalling high level ring beam- alternative location


GL C-D/4- under demolition/ prior to recast


chimney base- RJC/HUT to forward remedial proposals for comment


All builderswork to be in accordance with drawings- HUT confirm


CL.EW.00.15- lintol required high level internally


NEE to confirm proposals for comment to high level trays classroom corridor GFL


Door frames on site


Assembly screed to plant too high at door threshold


water internally to WC areas assembly hall- temporary drainage to be rectified


M&E works in progress- lobby to assembly main hall


RWP high level assembly


Water internally- temporary drainage to be rectified


GL Q/14- taping to be addressed to corner


taping around windposts high level assembly hall


Blanking panel- SecCo detail required- no brick ties


Colour mortar- gaps GL N/20


Wind post to be painted behind hit and miss brick panel


Grey perp vents required where not adjacent to heritage red header


Water ingress adjacent toilets Assembly GFL


Frieze pattern high level GL 20


GL 18 heritage red brickwork underway


Awaiting Ibstock specials courses 71,72,73


Lintol- HUT to confirm as AI 210


Ditto


Brick patterning from Ingrave Road