Friday, 24 September 2010

100923 Site Visit


Otway arch- still awaiting final Lambs drawings- no progress


Mortar pointing samples- on inconsistent/ stock bricks- additional samples to be carried out


lead/ gable detail underway Otway


Arch OT.01.15 still unpropped following damage


New slates underway


Valley detail underway


Insect mesh detail


First fix, secondary floor joists 1st floor Otway


First fix/ penetrations High level ground floor Otway


Different block specification- not Plasmor- HCL to confirm


GL A/7 reveal detail to be updated due to TEK cill detail/ movement joint


Ditto CL.EW.02.04


Ditto CL.EW.02.07


Raked cut to GL 4 high level


Link steelwork


Valley gutter installation underway classroom block


Remedial works to ties now undertaken


TEK to clarify strategy for Attenuated vent installation procedure


High level obstruction to attenuated vents 2nd floor- HCL to clarify fixing to underside of ringbeam


rods to be trimmed to allow acceptable tolerance for TEK vent


Openings for chimneys required high level ground floor GL B and C/ 1


CVA to confirm brick slips to concrete chimney base face


CVA to forward canopy detail, HRW to update structural connection


Chimney tie remedials underway


Ditto


Engineering brick penetrations- HCL to confirm possible remedial works to amend with FOSROC


Issue with high level steelwork to assembly mezzanine/ build up/ Vales works


Assembly hall ceiling 1st layer under installation


Classroom/ Otway overview


Assembly hall 1st floor lintels on site- HCL to forward brick slip details/ specs for comment


DGT expanding foam detail to valleys


Brick reveals underway GL 18 Assembly


GDT profile to be added to all locations where remedial works are underway


BJR to corners, GL Q/18


'V' detail GL Q/16 underway


High level corner nearing completion GL Q/14

Friday, 17 September 2010

100916 Site Visit


Overview from Ingrave Road


Classroom block gable brickwork underway to courtyard


Fixings for secondary grid- assembly hall


Area for remaining bricks lift to assembly- to commence shortly


DGT profiles adjacent gutters to be fitted- assembly roof


GL Q/14- bricks marked up to corner for amendments following previous comments


GL 18 brick reveals assembly hall


Corner underway GL Q/18


Latchway system installed to Bauder roof assembly hall


Assembly rooflights awaiting installation- main roof


Rooflight detail (to be rotated 180ยบ before installation)


Otway gable end (new facing brick) revealed


Arch repairs first floor Otway revealed


Lead detail against rebuilt chimney Otway


Valleys introduced Otway


Arch repair imminent- condition worsened


Bed joint reinforcement installed gable end classroom- courtyard


Block to be cut GL K/20


Protection to door linings classroom block


Link steel installed


High level raked steel angle trim


Possible service clash 1st floor classroom- CVA to advise regarding clerestory set out


Joinery schedule to be updated re: clerestory lights


TEK vent/ reveal


Concrete upstand detail- acoustic panel/ interface/ bead detail to be reviewed


Concrete remedials underway to chimney base classroom


Assembly overview- plinth


timber structure for rooflights underway


Pattern brick to chimneys internally- classroom block


DGT gutter installation underway- classroom block


Ties- cracking to ringbeam GL C


TSI remedials to trapezoid rooflight area


further tolerance req'd to top steel- HCL to fwd fixing detail option for HRW review


ditto


Floor joists first floor Otway


Link steelwork classroom/ Otway


Stanchion/ recess infill- CVA to confirm detail re: LAC support


Gutter for classroom on site


tolerance for linings to be reviewed


Link steel connection


Main chimney brickwork/ ringbeam interface


Chimney brickwork- movement joint


Link overview


Repair to corner underway- Queens