Friday, 26 November 2010

101125 Site Visit


Assembly Fireborn blue capping installed to plinth -special corner


ditto


Classroom lift installation underway


Internal brick exposed- but not ibstock- HCL to advise- not as CVA detail


Recessed now skimmed- awaiting wall lights


Light greypointing mortar currently being used to repoint (dabbed in centre) differ from Otway conservation officer approved mortar sample 6:1:1- HCL to advise


2nd floor plant trough underway- CL


Assembly gables in brick nearing completion


CL stairwell rooflight- main stair


CVA to instruct dryline fillet- to be coordinated with 2fl joinery- HCL to advise HTP- to form part of CVA comments on joinery


Containment to class stairs to be shallower bend to allow fixing of acoustic panels to u/side of stair


CVA to forward detail for lining to rooflight/ wall junction


Internal chimney underway classroom 11


trapezoid rooflight installed classroom 11


block awaiting acoustic seal- classroom block 1fl


patterned chimney complete classroom 8


Block/ prop detail to be resolved- GL C/7


TEK vents 1fl- awaiting cills- promised Mon 22 Nov


CVA to check detail of support with HRW


Brickwork badly stained, cill mods required, ringbeam mods required GL 4


GL 4 overview.


Setting out of brick gable geometry GL D to be clarified with HCL


Otway loft linings nearing completion


Otway stair lighting underway


Otway elec containment GFL underway- CVA to check levels/ items against drawings


Roof scape overview


DGT gutter to be modified to corner


DGT flashing closer piece installed


Awaiting adjusted gothic arch bricks from Lambs to be redelivered


Grille/ ducts behind hit and miss brickwork GFL plantroom- deviation from CVA/ MFLLP intent/ comments- HCL to advise


Ditto


Fireline underway to AS plantroom


Plastering underway to AS lobby GFL


Assembly Hall linings to main hall- corner fillets complete


Assembly gables nearing completion

Friday, 19 November 2010

101118 Site Visit


Assembly Hall GL 18 brickwork- gables now complete- awaiting Fireborn capping


Ditto


Decorative brickwork infill panel GL D/3 nears completion


1fl TEK vents delivered/ installation underway


TEK sill incorrect angle- TEK addressing and re-manufacturing/ fitting


Ditto


Containment/ fixing of cable tbc with MFLLP


Reveals to rooflights- Otway loft internal


Recessed lights to stairwell- Otway


beading details to Otway loft- awaiting plaster skim


Assembly lining underway- corner fillets to be completed. Vales/ Taylor engineering to confirm details for hanging fixings to raked internal lining GL P-Q


Hairline crack to brick horizontally over Ancon brickwork support GL 14- HRW to advise





Special bricks glued to lintol GL 18. HCL to forward tech specs/ method- still outstanding


Corner/ parapet GL Q/18. Timber/ insulation installation underway. DGT gutter to be cute down. Parapet awaiting Capping.


Ibstock Fireborn cappings now on site.


Gable detail GL 9- clearance acceptable


Inadequate clearance to brick upstand GL 1


Ditto


Gutter lower than outlet position- GL D/4


GL D/1- outlet finishing poor- HCL to advise


Ditto


Ditto


Internal gutter level to be lowered to parapet level- HCL to advise


Ditto


Edge detail poorly cut- HCL to advise


Hip detail refitted but GRP detail still tbc- HCL to advise


Outlet/ falls to valley gutter inadequate- HCL to advise


Detail/ intent not as CVA DWG CL330 PL01 + notes.- HCL to advise