Monday, 31 January 2011

110127-28 Site Visit


Tiling now commenced to Classroom block north elevation


Repairs to remaining areas Otway externally


Arch repair/ infill


Otway interior continues- awaiting plaster 1fl


Template from Lambs on site for arch


Club tiles/ lunettes complete to Otway GFL


Tiles to be instructed to fireplace


Colour to be confirmed for Otway cills


Chimney side linings now stepped back


Perimeter wall to be marked up for accurate repointing/ replacement quote- CVA


COI required for 2fl lining to chimney frame- back-to-back beads/ skim- HCL


DGT to provide closing piece to hipped roof element

Flush rooflight- tags for lightning protection required



Pattern tiling underway


Cut to gable end requires attention GL A/9


Pattern tiles


Assembly overview- roof battening commenced


Door linings to Otway- unprotected


Assembly minstrels drylining/ rad position


Drylining to bulkhead/ minstrel's gallery

Monday, 24 January 2011

110120 Site Visit


Otway Door lining queries- depth agreed- HCL to liaise with Shadbolts to confirm


CVA drawing denotes arch- CVA to confirm treatment to GFL Otway opening


AS green room wall commenced


Secco glazing on site


HTP samples on site-


WISA joinery sample door


Birds mouth detail stair panel option


Shadow gap detail stair panel option


CL roof battens underway


GRP nearing completion to CL roof


Battening to valley- CL block


Roofing detail not as Kingspan recommended- issued as transmittal K444, issued 12 Oct, '10


Battens to roof classroom block


Closer piece to be fitted by DGT


Blockwork to GL 14 underway for Fineline windows


AS Insulation/ flashing to parapet complete


Ply to underside of GL14 opening AS


AS mezzanine framing underway


Mist coat underway AS main hall


Vales mezzanine framing AS 1st floor


Brickwork to AS green room underway


Brick plinth to Ingrave Road- Scaffold struck


Classroom block- timber battening to roof


Teapoint door lining to Otway


Otway high level 1fl


2 coats to timber trusses


Slurry applied to chimney high level 1fl Otway


Ditto


Ditto


CVA confirmed to recess finish of infill boarding 50mm from slurried chimney


Ditto


Mech/ Elec access limited 2fl CL


Ditto- CVA to confirm if bulkhead required for electrical route into plantroom


Electrical 1st fix underway 2fl CL


Plastering 2fl CL


CVA to confirm lining around framing- Classroom 16 2fl


Rooflights Classroom 11


Large chimney- internal finish brickwork nearing completion


Classroom link- block complete


CVA to forward agreed detail for window boards/ linings


Tiling detail to toilets


Chimney internal insulation


Classroom 4 cabling


Otway roof remedials complete- CVA to check on site