Friday, 20 May 2011

110519 Site Visit


Footings to courtyard landscape walls


Cleaning to classroom brickwork still required


Classroom ground floor snagging


Assembly stair- handrail installation


CVA condemn Otway/ Assembly Junckers floor transition- 10mm discrepancy. HCL to now address


Otway perimeter landscape walls underway


Damp patch to Otway wall- not improving.


CL stair 1


Brick lights- issue regarding size- CVA to liaise with MFLLP regarding spec.


CL stair 1 soffit/ trim installed


Stair 2 nearing completion- final lacquer required


Gates to Ingrave Road re-installed


Soft landscape works ongoing to Ingrave Road side


Air test underway assembly hall


Praeposters/ tile transitions general to be address


Lean-to greenhouse removed


footings adjacent Queens


Greenhouse slab poured


Draw pit to be repositioned- current conflict with hard/ soft landscape transitions


Courtyard landscape underway- levels raised


Brickwork to be cleaned- classroom block


Landscape- courtyard


Gas pipes- CVA to check with MFLLP whether these can be grey as currently conspicuous


Soft landscape Ingrave Road


Otway/ Assembly overview


Landscape lighting- base to go on base course- top fitting to be masked to maintain access when final coat (resin-bound) is applied


Assembly green room lighting does not match specified fitting- HCL to advise

Monday, 16 May 2011

110512+13 Site Visit


Ingrave Road overview: Landscape base course laid/ kerbs installed


AS- harbo panelling installed- spindles for Salto too short- consult AC Leigh


AS- acoustic panel frames decorated


AS- stair nosing detail/ inset tread


AS- stair overview


CL- handrail to stair 2 underway- sweeping bends resolved


CL- stair 1- handrail completed- awaiting lacquer


CL- matwell installed


OT- perimeter landscape wall underway


CL- stair 1- infill panel to acoustic ceiling required GFL


Otway stair- lighting installed/ decs almost complete


CL- stair 1- alternative escape light required- CVA/ MFLLP to discuss


OT/AS- discrepancy in floor finish levels in transition- HCL to advise/ propose solution


Otway arch- 2 No. repairs required


AS- plinth landscape capping complete- awaiting block pavers/ manholes


ditto


AS- soft landscape to perimeter underway


Minor additional repointing required to Ingrave Road wall


Tree stumps- to be grubbed/ removed


AS- awaiting soffit panels


Praeposters court- hard landscape complete- Otway door decoration required


GEN: Window linings generally require rub down/ redec.


GFL classroom 1- grilles installed- making good/ redec required


CL stair panels installed Stair


Green room- flashing required for return glazing


AS plant room- repair to damaged brickwork required


AS_ plinth completed- awaiting resin bound gravel final coat


PR- courtyard landscape footings underway